12931 | Worthington Mill Rd Br (Bridge) (Northampton Township & Wrightstown Township, Bucks County)
This project involves bridge rehabilitation or replacement of state bridge over the Neshaminy Creek on Worthington Mill Road between Swamp Road and Twining Bridge Road in Northampton and Wrightstown Townships. It is a poor condition bridge breakout project from MPMS #88706. A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.
Limits: NORTHAMPTON & WRIGHTSTOWN TWPS
Air Quality Code: S19
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
ROW | STP | $0 | $0 | $0 | $0 | $0 |
UTL | STP | $0 | $0 | $0 | $0 | $0 |
Program Year Totals: | $0 | $0 | $0 | $0 | ||
Total FY23-FY26 Cost: | $0 | Total FY23-FY34 Cost: | $0 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
CON | Final ROW Clearance | |
CON | Final Utility Clearance | |
CON | Start of Phase | 2022-06-21 |
CON | Let | 2022-07-14 |
CON | Award Contract | 2022-05-21 |
CON | Notice to Proceed | 2022-08-29 |
CON | Phase on Approved STIP | |
CON | Physical Work Complete | 2024-05-04 |
CON | Completion of Phase | 2024-12-15 |
CON | Project Agreement End Date | 2025-11-26 |