119415 | Jefferson Station Escalators FLEX
This project is for the replacement of four escalators at the Convention Center and Jefferson Station and the flexing of funds over to SEPTA.
Limits: Jefferson Station, Center City Philadelphia
Air Quality Code: NRS
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
CON | sSTP | $2000 | $0 | $0 | $0 | $0 |
Program Year Totals: | $2,000 | $0 | $0 | $0 | ||
Total FY23-FY26 Cost: | $2,000 | Total FY23-FY34 Cost: | $2,000 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
CON | Start of Phase | 2022-12-01 |
CON | Completion of Phase | 2023-11-30 |