119301 | District 6-0 Systemwide Pedestrian Countdown Signals
This project will implement a system wide safety improvement for vulnerable road users (VRUs) by implementing Pedestrian countdown timers. This will require several different tiered projects based on the level of effort to install PCTs. The complexity varies for each location.
Limits: Districtwide
Air Quality Code: M6
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
PE | sHSIP | $2165 | $0 | $0 | $0 | $0 |
CON | sHVRU | $0 | $2000 | $3052 | $0 | $0 |
Program Year Totals: | $2,165 | $2,000 | $3,052 | $0 | ||
Total FY23-FY26 Cost: | $7,217 | Total FY23-FY34 Cost: | $7,217 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
PE | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
PE | Start of Phase | 2022-11-15 |
PE | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
PE | 4232 Approved by FHWA | |
PE | Completion of Phase | 2023-08-31 |
CON | Let | 2023-09-14 |
CON | Award Contract | 2023-10-14 |
CON | Notice to Proceed | 2023-11-13 |
CON | Start of Phase | 2023-11-13 |
CON | Physical Work Complete | 2025-09-30 |
CON | Completion of Phase | 2025-11-29 |
CON | Project Agreement End Date | 2027-03-31 |