❮ Back

118386 | Roosevelt Boulevard at Southampton Road (Statewide "MTF")

This project will construct intersection improvements at SR 1 (Roosevelt Blvd.) and Southampton Road, including driveways on SR 1 and Southampton Road. Improvements will add turning lanes, new signalized and reconfiguration of existing signalized intersection.

Limits: SR 1 (Roosevelt Blvd) and Southampton Rd
Air Quality Code: X12

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
CONLOC$5135$0$0$0$0
CON411$3000$0$0$0$0
Program Year Totals:$8,135$0$0$0 
Total FY23-FY26 Cost:$8,135Total FY23-FY34 Cost:$8,135 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
CONPhase Approved by PMC
CONLet2023-09-14
CONAward Contract2023-10-14
CONNotice to Proceed2023-11-13
CONStart of Phase2023-11-13
CONPhysical Work Complete2025-04-08
CONCompletion of Phase2025-06-07
CONProject Agreement End Date2026-10-07