118356 | Liberty Bell Trail (Montgomery County)
This project will construct a multi-use trail.
Limits: Orvilla road
Hatfield Township
Orvilla Road
Air Quality Code: A2
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
CON | TAP | $0 | $550 | $360 | $0 | $0 |
Program Year Totals: | $0 | $550 | $360 | $0 | ||
Total FY23-FY26 Cost: | $910 | Total FY23-FY34 Cost: | $910 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
CON | Phase on Approved STIP | |
CON | Let | 2024-09-26 |
CON | Award Contract | 2024-10-26 |
CON | Notice to Proceed | 2024-11-25 |
CON | Start of Phase | 2024-11-25 |
CON | Physical Work Complete | 2025-09-15 |
CON | Completion of Phase | 2025-11-14 |
CON | Project Agreement End Date | 2027-03-16 |