This project will make crosswalk striping, ADA Ramps and landing strips
Limits: West Cobbs Creek, Church, Chester Ave, and MacDade
Air Quality Code: A2
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
CON | TAP | $0 | $600 | $400 | $0 | $0 |
Program Year Totals: | $0 | $600 | $400 | $0 | ||
Total FY23-FY26 Cost: | $1,000 | Total FY23-FY34 Cost: | $1,000 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
CON | Phase on Approved STIP | |
CON | Start of Phase | 2023-08-01 |
CON | Completion of Phase | 2026-08-01 |