118032 | Dekalb Street Two-Way Reconstruction (Norristown Borough, Montgomery County)
The project will fund full-depth reconstruction of the final remaining segment of US 202 in Montgomery County, along with restriping and traffic signal installation to permit two-way traffic along DeKalb Street in the Municipality of Norristown.
Limits: Lafayette Street to Johnson Highway
Air Quality Code: 2035M
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
PE | STU | $0 | $500 | $0 | $0 | $0 |
FD | 581 | $0 | $0 | $0 | $0 | $1500 |
ROW | 581 | $0 | $0 | $0 | $0 | $250 |
UTL | 581 | $0 | $0 | $0 | $0 | $500 |
CON | STU | $0 | $0 | $0 | $0 | $6000 |
Program Year Totals: | $0 | $500 | $0 | $0 | ||
Total FY23-FY26 Cost: | $500 | Total FY23-FY34 Cost: | $8,750 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
PE | Phase Approved by PMC | |
PE | Phase on Approved STIP | |
CON | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
PE | Start of Phase | 2022-10-30 |
PE | Completion of Phase | 2023-10-30 |
FD | Start of Phase | 2023-10-30 |
ROW | Start of Phase | 2024-10-30 |
UTL | Start of Phase | 2024-10-30 |
FD | Completion of Phase | 2024-10-30 |
UTL | Completion of Phase | 2025-10-30 |
ROW | Completion of Phase | 2025-10-30 |
CON | Start of Phase | 2025-10-30 |
CON | Completion of Phase | 2028-10-30 |