118032 | Dekalb Street Two-Way Reconstruction (Norristown Borough, Montgomery County)

The project will fund full-depth reconstruction of the final remaining segment of US 202 in Montgomery County, along with restriping and traffic signal installation to permit two-way traffic along DeKalb Street in the Municipality of Norristown.

Limits: Lafayette Street to Johnson Highway
Air Quality Code: 2035M

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
PESTU$0$500$0$0$0
FD581$0$0$0$0$1500
ROW581$0$0$0$0$250
UTL581$0$0$0$0$500
CONSTU$0$0$0$0$6000
Program Year Totals:$0$500$0$0 
Total FY23-FY26 Cost:$500Total FY23-FY34 Cost:$8,750 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
PEPhase Approved by PMC
PEPhase on Approved STIP
CONPhase Approved by PMC
ROWPhase Approved by PMC
UTLPhase Approved by PMC
FDPhase Approved by PMC
PEStart of Phase2022-10-30
PECompletion of Phase2023-10-30
FDStart of Phase2023-10-30
ROWStart of Phase2024-10-30
UTLStart of Phase2024-10-30
FDCompletion of Phase2024-10-30
UTLCompletion of Phase2025-10-30
ROWCompletion of Phase2025-10-30
CONStart of Phase2025-10-30
CONCompletion of Phase2028-10-30