118031 | PA 29 & PA 113 (Perkiomen Township, Montgomery County)

This project will provide left turn lanes at all four approaches, a right turn lane on the southbound approach of SR 113, update signals and ADA ramps, and provide crosswalks

Air Quality Code: R1

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
PESTP$413$0$0$0$0
PESTU$636$0$0$0$0
FD581$0$0$0$0$900
ROW581$0$0$0$0$300
UTL581$0$0$0$0$200
CONSTU$0$0$0$0$2738
CON581$0$0$0$0$262
Program Year Totals:$1,049$0$0$0 
Total FY23-FY26 Cost:$1,049Total FY23-FY34 Cost:$5,449 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
FDPhase Approved by PMC
UTLPhase Approved by PMC
CONPhase Approved by PMC
ROWPhase Approved by PMC
PEPhase Approved by PMC
PEPhase on Approved STIP
PEStart of Phase2023-05-01
ROWStart of Phase2023-10-30
ROWCompletion of Phase2024-10-30
UTLStart of Phase2024-10-30
FDCompletion of Phase2024-10-30
PEN. E. P. A. Approval2025-01-05
PECompletion of Phase2025-02-04
FDStart of Phase2025-02-04
UTLPlan to Utility Unit2025-09-01
ROWPlan to ROW Unit2025-09-01
CONLet2025-09-17
CONAward Contract2025-10-17
CONStart of Phase2025-10-30
UTLCompletion of Phase2025-10-30
FDPS+E to District Contract Management2026-07-01
CONPhysical Work Complete2026-12-15
CONCompletion of Phase2027-02-13
CONProject Agreement End Date2028-06-14