118029 | Bethel Roundabout (Bethel Township, Delaware County)
Reconfigure the intersection to accommodate a roundabout to address the congestion at the intersection of Concord/Chelsea/Valleybrook/Foulk Rd Intersection.
This road segment is included in the Delaware County Bicycle Plan.
Limits: Concord and Foulk- Concord and Chelsea/Valleybrook
Air Quality Code: 2035M
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
PE | STU | $0 | $250 | $0 | $0 | $0 |
FD | STP | $0 | $0 | $0 | $0 | $150 |
ROW | STP | $0 | $0 | $0 | $0 | $320 |
UTL | STP | $0 | $0 | $0 | $0 | $300 |
CON | STP | $0 | $0 | $0 | $0 | $2750 |
Program Year Totals: | $0 | $250 | $0 | $0 | ||
Total FY23-FY26 Cost: | $250 | Total FY23-FY34 Cost: | $3,770 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
PE | Phase Approved by PMC | |
PE | Phase on Approved STIP | |
CON | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
PE | Start of Phase | 2022-10-30 |
PE | 4232 Approved by FHWA | |
PE | Completion of Phase | 2023-10-30 |
FD | Start of Phase | 2023-10-31 |
FD | Completion of Phase | 2024-10-30 |
UTL | Start of Phase | 2024-10-31 |
ROW | Start of Phase | 2024-10-31 |
ROW | Completion of Phase | 2025-10-31 |
UTL | Completion of Phase | 2025-10-31 |
CON | Start of Phase | 2027-10-30 |
CON | Completion of Phase | 2029-10-30 |
CON | Project Agreement End Date | 2030-02-28 |