118022 | Route 202/179 Roundabout (Solebury Township, Bucks County)
The intersection of Route 202 and Route 179 will be replaced with a roundabout. Surrounding driveways will be realigned to function more efficiently. Pedestrian movements will be improved.
Air Quality Code: 2035M
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
PE | STU | $855 | $0 | $0 | $0 | $0 |
FD | STU | $0 | $0 | $0 | $0 | $250 |
ROW | STU | $0 | $0 | $0 | $0 | $500 |
UTL | STU | $0 | $0 | $0 | $0 | $250 |
CON | STU | $0 | $0 | $0 | $0 | $8000 |
Program Year Totals: | $855 | $0 | $0 | $0 | ||
Total FY23-FY26 Cost: | $855 | Total FY23-FY34 Cost: | $9,855 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
PE | Phase Approved by PMC | |
PE | Phase on Approved STIP | |
FD | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
PE | 4232 Approved by FHWA | |
PE | Completion of Phase | 2024-10-01 |
PE | Start of Phase | 2023-03-06 |
PE | N. E. P. A. Approval | 2024-09-01 |
FD | Start of Phase | 2024-10-01 |
ROW | Start of Phase | 2024-10-30 |
UTL | Start of Phase | 2024-10-30 |
FD | Completion of Phase | 2024-10-30 |
UTL | Plan to Utility Unit | 2024-12-01 |
ROW | Plan to ROW Unit | 2024-12-01 |
FD | PS+E to District Contract Management | 2025-09-01 |
ROW | Completion of Phase | 2025-10-30 |
CON | Start of Phase | 2025-10-30 |
UTL | Completion of Phase | 2025-10-30 |
CON | Let | 2025-12-04 |
CON | Award Contract | 2026-01-03 |
CON | Physical Work Complete | 2026-12-31 |
CON | Completion of Phase | 2027-03-01 |
CON | Project Agreement End Date | 2028-06-30 |