118020 | Bustleton Pike/Second Street Pike Roundabout (Northampton Township, Bucks County)
The intersection of Second Street Pike and Bustleton Pike will be replaced with a roundabout and a fourth leg will be added to connect to Township Road. Surrounding driveways will be realigned to function more efficiently. Pedestrian movements will be improved. The Township has completed preliminary design, but the design will need to be brought up to federal standards.
Air Quality Code: 2035M
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
PE | STU | $250 | $0 | $0 | $0 | $0 |
ROW | STU | $0 | $0 | $0 | $0 | $122 |
ROW | 581 | $0 | $0 | $0 | $0 | $228 |
UTL | STU | $0 | $0 | $0 | $0 | $125 |
CON | STU | $0 | $0 | $0 | $0 | $5000 |
Program Year Totals: | $250 | $0 | $0 | $0 | ||
Total FY23-FY26 Cost: | $250 | Total FY23-FY34 Cost: | $5,725 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
FD | Phase on Approved STIP | |
FD | Phase Approved by PMC | |
FD | Start of Phase | 2023-05-31 |
ROW | Plan to ROW Unit | 2023-12-15 |
UTL | Start of Phase | 2023-12-15 |
FD | PS+E to District Contract Management | 2024-06-01 |
CON | Let | 2024-08-22 |
CON | Award Contract | 2024-09-21 |
ROW | Completion of Phase | 2025-07-01 |
FD | Completion of Phase | 2025-07-02 |
CON | Physical Work Complete | 2026-12-15 |
CON | Completion of Phase | 2027-02-13 |
UTL | Completion of Phase | 2027-07-02 |
CON | Project Agreement End Date | 2028-06-14 |