118020 | Bustleton Pike/Second Street Pike Roundabout (Northampton Township, Bucks County)

The intersection of Second Street Pike and Bustleton Pike will be replaced with a roundabout and a fourth leg will be added to connect to Township Road. Surrounding driveways will be realigned to function more efficiently. Pedestrian movements will be improved. The Township has completed preliminary design, but the design will need to be brought up to federal standards.

Air Quality Code: 2035M

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
PESTU$250$0$0$0$0
ROWSTU$0$0$0$0$122
ROW581$0$0$0$0$228
UTLSTU$0$0$0$0$125
CONSTU$0$0$0$0$5000
Program Year Totals:$250$0$0$0 
Total FY23-FY26 Cost:$250Total FY23-FY34 Cost:$5,725 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
CONPhase Approved by PMC
ROWPhase Approved by PMC
UTLPhase Approved by PMC
FDPhase on Approved STIP
FDPhase Approved by PMC
FDStart of Phase2023-05-31
ROWPlan to ROW Unit2023-12-15
UTLStart of Phase2023-12-15
FDPS+E to District Contract Management2024-06-01
CONLet2024-08-22
CONAward Contract2024-09-21
ROWCompletion of Phase2025-07-01
FDCompletion of Phase2025-07-02
CONPhysical Work Complete2026-12-15
CONCompletion of Phase2027-02-13
UTLCompletion of Phase2027-07-02
CONProject Agreement End Date2028-06-14