117953 | Newtown Rail Trail P2 (Bucks County)
This project involves constructing an extension (1.7 miles) of the Newtown Rail Trail from Bristol Road to Churchville Nature Center.
Limits: Bristol Road to Churchville Nature Center
Air Quality Code: A2
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
CON | TAP | $0 | $470 | $0 | $0 | $0 |
Program Year Totals: | $0 | $470 | $0 | $0 | ||
Total FY23-FY26 Cost: | $470 | Total FY23-FY34 Cost: | $470 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Start of Phase | 2022-07-01 |
CON | Phase Approved by PMC | |
CON | Phase on Approved STIP | |
CON | Completion of Phase | 2025-12-30 |