117793 | Systemic Improvements - Lane Departure (Various)
This project uses a systemic approach to identify locations that have an overrepresentation of fatal and serious injury lane departure crashes in curves where low-cost safety countermeasures can be constructed to reduce the number and severity of crashes.
Air Quality Code: S6
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
PE | sHSIP | $1000 | $0 | $0 | $0 | $0 |
CON | sHSIP | $2000 | $3920 | $0 | $0 | $0 |
Program Year Totals: | $3,000 | $3,920 | $0 | $0 | ||
Total FY23-FY26 Cost: | $6,920 | Total FY23-FY34 Cost: | $6,920 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
PE | Phase Approved by PMC | |
PE | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
CON | Phase Approved by PMC | |
PE | Start of Phase | 2022-10-13 |
PE | 4232 Approved by FHWA | |
CON | Let | 2023-08-24 |
CON | Award Contract | 2023-09-23 |
PE | Completion of Phase | 2023-10-12 |
CON | Start of Phase | 2023-10-23 |
CON | Notice to Proceed | 2023-10-23 |
CON | Physical Work Complete | 2026-03-27 |
CON | Completion of Phase | 2026-05-26 |
CON | Project Agreement End Date | 2027-09-25 |