117793 | Systemic Improvements - Lane Departure (Various)

This project uses a systemic approach to identify locations that have an overrepresentation of fatal and serious injury lane departure crashes in curves where low-cost safety countermeasures can be constructed to reduce the number and severity of crashes.

Air Quality Code: S6

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
PEsHSIP$1000$0$0$0$0
CONsHSIP$2000$3920$0$0$0
Program Year Totals:$3,000$3,920$0$0 
Total FY23-FY26 Cost:$6,920Total FY23-FY34 Cost:$6,920 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
PEPhase Approved by PMC
PEPhase on Approved STIP
CONPhase on Approved STIP
CONPhase Approved by PMC
PEStart of Phase2022-10-13
PE4232 Approved by FHWA
CONLet2023-08-24
CONAward Contract2023-09-23
PECompletion of Phase2023-10-12
CONStart of Phase2023-10-23
CONNotice to Proceed2023-10-23
CONPhysical Work Complete2026-03-27
CONCompletion of Phase2026-05-26
CONProject Agreement End Date2027-09-25