116893 | Edison Furlong Road over Pebble Creek (Buckingham Township, Bucks County)

Improvements include replacing the scour damaged bridge over Pebble Creek pursuant to damage caused by Hurricane Ida.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.

Air Quality Code: S19

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
PESTP$300$0$0$0$0
FDSTP$0$25$0$0$0
CONSTP$0$0$800$0$0
Program Year Totals:$300$25$800$0 
Total FY23-FY26 Cost:$1,125Total FY23-FY34 Cost:$1,125 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
CONPhase on Approved STIP
PEPhase on Approved STIP
PEPhase Approved by PMC
CONPhase Approved by PMC
FDPhase Approved by PMC
FDPhase on Approved STIP
PEStart of Phase2022-12-05
PE4232 Approved by FHWA
PEN. E. P. A. Approval2024-05-31
FDStart of Phase2024-06-30
PECompletion of Phase2024-06-30
FDPS+E to District Contract Management2025-09-11
CONLet2025-12-11
CONAward Contract2026-01-10
CONStart of Phase2026-02-09
CONNotice to Proceed2026-02-09
FDCompletion of Phase2026-02-09
CONPhysical Work Complete2026-10-30
CONCompletion of Phase2026-12-29
CONProject Agreement End Date2028-04-29