116879 | Ida Roadway Repairs FAS (Bucks County)

This project will make improvements include repairing and reconstructing eroded roadways and shoulders damaged during Hurriance Ida. These repairs are federally funded.
11/03/2022--Project let, District control has been changed from HNTB/N.Velaga to CONSTR. Low bidder was J.D. Eckman with a low bid amount of $1,784,741.

Limits: Bucks and Montgomery Counties
Air Quality Code: X13

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
CONFFL$67$0$0$0$0
CON581$17$0$0$0$0
Program Year Totals:$84$0$0$0 
Total FY23-FY26 Cost:$84Total FY23-FY34 Cost:$84 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
CONPhase Approved by PMC
CONFinal Utility Clearance
CON4232 Approved by FHWA
CONCompletion of Phase2023-10-24
CONPhase on Approved STIP
CONLet2022-11-03
CONAward Contract2022-12-03
CONNotice to Proceed2022-12-19
CONStart of Phase2023-01-02
CONPhysical Work Complete2023-04-13
CONProject Agreement End Date2025-02-22