116837 | Schuylkill Road over Eckers Creek (Chester County)
Bridge replacement to repair damage pursuant to Hurricane Ida. Schuylkill Rd over Eckers Ck, North Coventry Twp, Chester County
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
PE | 582 | $4 | $0 | $0 | $0 | $0 |
PE | FFL | $16 | $0 | $0 | $0 | $0 |
CON | 582 | $25 | $0 | $0 | $0 | $0 |
CON | FFL | $100 | $0 | $0 | $0 | $0 |
Program Year Totals: | $145 | $0 | $0 | $0 | ||
Total FY23-FY26 Cost: | $145 | Total FY23-FY34 Cost: | $145 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
PE | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
PE | 4232 Approved by FHWA | |
PE | Start of Phase | 2021-12-09 |
PE | N. E. P. A. Approval | |
PE | Programmatic CE | |
CON | Final ROW Clearance | |
CON | 4232 Approved by FHWA | |
CON | Final Utility Clearance | |
CON | Let | 2022-07-14 |
PE | Completion of Phase | 2022-07-01 |
CON | Notice to Proceed | 2022-06-27 |
CON | Award Contract | 2022-07-27 |
CON | Start of Phase | 2022-08-26 |
CON | Phase on Approved STIP | |
PE | Phase on Approved STIP | |
CON | Open to Traffic | 2022-10-21 |
CON | Completion of Phase | 2022-11-01 |
CON | Physical Work Complete | 2022-12-30 |
CON | Project Agreement End Date | 2024-04-17 |