116728 | Callowhill Road Over Branch Pleasant Spring (Bucks County)
This project will replace the existing bridge at Callowhill Road over Branch of Pleasant Spring Creek pursuant to damage from Hurricane Ida.
Limits: Callowhill Road over Branch Pleasant Spring Ck
Air Quality Code: S19
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
CON | FFL | $1185 | $395 | $0 | $0 | $0 |
CON | 582 | $296 | $99 | $0 | $0 | $0 |
Program Year Totals: | $1,481 | $494 | $0 | $0 | ||
Total FY23-FY26 Cost: | $1,975 | Total FY23-FY34 Cost: | $1,975 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Final Utility Clearance | |
ROW | Phase Approved by PMC | |
ROW | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
CON | Phase Approved by PMC | |
CON | Start of Phase | 2022-10-31 |
CON | Notice to Proceed | 2022-10-31 |
ROW | Plan to ROW Unit | 2023-02-15 |
ROW | Start of Phase | 2023-02-15 |
ROW | 4232 Approved by FHWA | |
ROW | Completion of Phase | 2023-08-15 |
CON | Let | 2023-08-24 |
CON | Award Contract | 2023-09-23 |
CON | Physical Work Complete | 2024-09-24 |
CON | Completion of Phase | 2024-11-23 |
CON | Project Agreement End Date | 2026-03-25 |