115974 | District 6 Modeling Assistance 2022-23 (Montgomery County)

This project provides for technical and planning assistance to PennDOT District 6 for support in implementation of the I-95 Reconstruction Projects, and other traffic studies as identified by PennDOT. DVRPC will be on call for quick-turnaround analysis or data collection tasks in support of specific and timely I-95 project planning needs. Tasks will include data collection, meeting and stakeholder coordination, traffic modeling and forecasting, and general research as needed.
This project will dedicate two-person years of DVRPC modeling staff time to prepare traffic forecasts throughout the I-95 corridor in Pennsylvania and on other District 6 projects as required. The staff members will report to the Manager, Office of Travel Trends and Forecasts, and work with other staff as needed to prepare traffic forecasts and other modeling services.
New traffic data and forecasts are needed for several tasks. These include analyzing additional interchange configurations to improve safety, reduce congestion, and address community concerns; support new or updated Point-of-Access (POA) studies; extend the horizon year of previous traffic forecasts in the corridor; analyze and plan for future freight activity; and prepare detour route forecasts for later construction phases.
Tasks
1. Coordinate with PennDOT and their consultants; attend meetings and make presentations as needed.
2. Focus and calibrate regional travel demand model on the I-95 corridor, and other facilities as needed.
3. Conduct computerized traffic assignments to determine horizon year traffic volumes under No-Build and Build scenarios.
4. Prepare average weekday daily traffic (AWDT) traffic volumes for I-95 mainline, ramps, and selected facilities impacted by the I-95 scenarios throughout Sectors A, B, C, and D.
5. Prepare AM and PM peak hour traffic forecasts, including intersection turning movements for the No-Build and Build scenarios, as needed.
6. Collect, tabulate, and/or process origin-destination and travel time data, as needed.
7. Prepare forecasts to evaluate the impact of new or improved transit connections on highway patterns, volumes, and interchange operations, as needed.
8. Prepare forecasts to evaluate the impacts of new land uses and/or redevelopment on travel patterns, volumes, and interchange operations, as needed.
9. Prepare maps and tables for transmittal of the data and travel forecasts to PennDOT and their consultants.
10. Prepare technical memorandums documenting the results of the travel forecasting; incorporate any comments from PennDOT and their consultants.
11. Continue supporting PennDOT's consultants for US 422 and the Market Street Bridge Closure modeling efforts.
12. Provide daily traffic forecasts the six proposed movements at the I-95 and PA Turnpike interchange.

Limits: I-95 Reconstruction areas, other areas as needed across the District
Air Quality Code: X1

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
PRA581$92$92$0$0$0
PRANHPP$368$368$0$0$0
Program Year Totals:$460$460$0$0 
Total FY23-FY26 Cost:$920Total FY23-FY34 Cost:$920 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
PRAPhase Approved by PMC
PRA4232 Approved by FHWA
PRAStart of Phase2022-07-01
PRAPhase on Approved STIP
PRACompletion of Phase2023-07-31