115445 | 5th Street Corridor Safety Improvements (Philadelphia City)
The proposed scope of this project include:
· Convert all signals from pedestal to mast arm from Spring Garden Street to Lycoming Street
· Install pedestrian countdown timer signal heads from Spring Garden Street to Lycoming Street
Limits: Spring Garden Street to Hunting Park Avenue
Air Quality Code: S6
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
PE | HSIP | $350 | $0 | $0 | $0 | $0 |
FD | HSIP | $400 | $0 | $0 | $0 | $0 |
CON | HSIP | $0 | $2000 | $2658 | $0 | $0 |
Program Year Totals: | $750 | $2,000 | $2,658 | $0 | ||
Total FY23-FY26 Cost: | $5,408 | Total FY23-FY34 Cost: | $5,408 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
FD | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
FD | Start of Phase | 2023-05-01 |
FD | PS+E to District Contract Management | 2025-11-01 |
CON | Let | 2026-02-12 |
CON | Award Contract | 2026-03-14 |
FD | Completion of Phase | 2026-04-13 |
CON | Start of Phase | 2026-04-13 |
CON | Notice to Proceed | 2026-04-13 |
CON | Physical Work Complete | 2027-07-01 |
CON | Completion of Phase | 2027-08-30 |
CON | Project Agreement End Date | 2028-12-29 |