115445 | 5th Street Corridor Safety Improvements (Philadelphia City)

The proposed scope of this project include:
· Convert all signals from pedestal to mast arm from Spring Garden Street to Lycoming Street
· Install pedestrian countdown timer signal heads from Spring Garden Street to Lycoming Street

Limits: Spring Garden Street to Hunting Park Avenue
Air Quality Code: S6

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
PEHSIP$350$0$0$0$0
FDHSIP$400$0$0$0$0
CONHSIP$0$2000$2658$0$0
Program Year Totals:$750$2,000$2,658$0 
Total FY23-FY26 Cost:$5,408Total FY23-FY34 Cost:$5,408 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
CONPhase Approved by PMC
FDPhase Approved by PMC
FDPhase on Approved STIP
CONPhase on Approved STIP
FDStart of Phase2023-05-01
FDPS+E to District Contract Management2025-11-01
CONLet2026-02-12
CONAward Contract2026-03-14
FDCompletion of Phase2026-04-13
CONStart of Phase2026-04-13
CONNotice to Proceed2026-04-13
CONPhysical Work Complete2027-07-01
CONCompletion of Phase2027-08-30
CONProject Agreement End Date2028-12-29