❮ Back

115435 | 63rd Street Corridor Safety Improvements (Philadelphia City)

The proposed scope of this project include:
• Adding lane lines on corridor – the corridor is two lanes in each direction for the majority of the length but pavement markings are not currently visible to drivers.
• Upgrading signal equipment by replacing 8” signal heads with 12” signal heads, installing retroflective back plates, adding additional signal heads (one for each lane, currently only one head per approach), installing countdown pedestrian signal heads.
• Evaluating and updating left-turn phasing at several intersections with a high number of angle crashes for left-turning vehicles.
• Evaluating and updating vehicle and pedestrian clearance timings.
• Convert the signalized intersection of Cobbs Creek Parkway (SR 3015) and Spruce Street/Marshall Road (SR 3031) to a single-lane roundabout.

Limits: 63rd Street/Cobbs Creek Parkway corridor from Lancaster Ave (SR 0030) to 62nd Street
Air Quality Code: 2035M

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
PE581$1000$1000$0$0$0
FDHSIP$342$0$0$0$0
ROWHSIP$91$0$0$0$0
CONHSIP$0$0$5209$1088$0
Program Year Totals:$1,433$1,000$5,209$1,088 
Total FY23-FY26 Cost:$8,730Total FY23-FY34 Cost:$8,730 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
FDPhase Approved by PMC
CONPhase Approved by PMC
ROWPhase Approved by PMC
FDStart of Phase2022-02-01
ROWStart of Phase2022-02-01
ROWPhase on Approved STIP
FDPhase on Approved STIP
CONPhase on Approved STIP
ROWCompletion of Phase2022-10-01
CONLet2024-01-25
CONAward Contract2024-02-24
CONStart of Phase2024-03-25
FDCompletion of Phase2024-03-25
CONNotice to Proceed2024-03-25
CONPhysical Work Complete2024-03-31
CONCompletion of Phase2024-05-30
CONProject Agreement End Date2025-09-29