115433 | Welsh Road Corridor Safety Improvements (Philadelphia City)
The proposed scope of this project include:
• Road diet of Welsh Road from Alburger Avenue to Kismet Road
• Addition of exclusive left turn lane(s) (LTLs)
• Addition of pedestrian countdown timers at signalized intersections
• Coordination of arterial signals
• Installation of retroreflective backplates on signals
Limits: Alburger Avenue to Kismet Road
Air Quality Code: 2025M
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
FD | HSIP | $105 | $0 | $0 | $0 | $0 |
UTL | HSIP | $312 | $0 | $0 | $0 | $0 |
CON | HSIP | $2640 | $301 | $0 | $0 | $0 |
Program Year Totals: | $3,057 | $301 | $0 | $0 | ||
Total FY23-FY26 Cost: | $3,358 | Total FY23-FY34 Cost: | $3,358 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
FD | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
UTL | Start of Phase | 2021-03-01 |
UTL | Completion of Phase | 2021-10-01 |
UTL | Plan to Utility Unit | 2022-01-15 |
FD | Start of Phase | 2022-08-26 |
CON | Phase on Approved STIP | |
FD | Phase on Approved STIP | |
UTL | Phase on Approved STIP | |
FD | 4232 Approved by FHWA | |
FD | PS+E to District Contract Management | 2023-07-14 |
CON | Let | 2023-09-14 |
CON | Award Contract | 2023-10-14 |
CON | Notice to Proceed | 2023-11-13 |
CON | Start of Phase | 2023-11-13 |
FD | Completion of Phase | 2023-11-13 |
CON | Physical Work Complete | 2024-10-01 |
CON | Completion of Phase | 2024-11-30 |
CON | Project Agreement End Date | 2026-04-01 |