115431 | Verree Rd Corridor Safety Improvements (Philadelphia City)
The proposed scope of this project include:
• Conversion of signals from pedestal-mounted to mast arm
• Addition of pedestrian countdown timers and pushbuttons
• Coordination of arterial signals
• Modification of left turn signal phasing at Welsh Road
Limits: Bloomfield Avenue to Red Lion Road
Air Quality Code: 2025M
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
FD | HSIP | $201 | $0 | $0 | $0 | $0 |
CON | HSIP | $3860 | $344 | $0 | $0 | $0 |
Program Year Totals: | $4,061 | $344 | $0 | $0 | ||
Total FY23-FY26 Cost: | $4,405 | Total FY23-FY34 Cost: | $4,405 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
FD | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
FD | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
FD | Start of Phase | 2022-10-15 |
FD | 4232 Approved by FHWA | |
FD | PS+E to District Contract Management | 2023-07-14 |
FD | Completion of Phase | 2023-08-07 |
CON | Let | 2023-09-14 |
CON | Award Contract | 2023-10-14 |
CON | Start of Phase | 2023-11-13 |
CON | Notice to Proceed | 2023-11-13 |
CON | Physical Work Complete | 2024-10-01 |
CON | Completion of Phase | 2024-11-30 |
CON | Project Agreement End Date | 2026-04-01 |