115430 | Broad Street Corridor Safety Improvements (Philadelphia City)
This project will implement the replacement of the two-way left-turn lane with raised concrete medians with pedestrian refuges.
Limits: Allegheny Avenue to the Roosevelt Boulevard
Air Quality Code: S6
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
FD | HSIP | $63 | $0 | $0 | $0 | $0 |
UTL | HSIP | $0 | $56 | $0 | $0 | $0 |
CON | HSIP | $0 | $826 | $0 | $0 | $0 |
CON | CRPU | $1300 | $0 | $0 | $0 | $0 |
Program Year Totals: | $1,363 | $882 | $0 | $0 | ||
Total FY23-FY26 Cost: | $2,245 | Total FY23-FY34 Cost: | $2,245 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
UTL | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
UTL | Start of Phase | 2022-02-01 |
CON | Phase on Approved STIP | |
FD | Phase on Approved STIP | |
UTL | Phase on Approved STIP | |
UTL | Completion of Phase | 2022-10-31 |
FD | Start of Phase | 2023-03-31 |
UTL | Plan to Utility Unit | 2023-05-01 |
FD | PS+E to District Contract Management | 2023-12-01 |
FD | Completion of Phase | 2024-01-01 |
CON | Let | 2024-03-14 |
CON | Award Contract | 2024-04-13 |
CON | Start of Phase | 2024-05-13 |
CON | Notice to Proceed | 2024-05-13 |
CON | Physical Work Complete | 2025-07-01 |
CON | Completion of Phase | 2025-08-30 |
CON | Project Agreement End Date | 2026-12-30 |