115430 | Broad Street Corridor Safety Improvements (Philadelphia City)

This project will implement the replacement of the two-way left-turn lane with raised concrete medians with pedestrian refuges.

Limits: Allegheny Avenue to the Roosevelt Boulevard
Air Quality Code: S6

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
FDHSIP$63$0$0$0$0
UTLHSIP$0$56$0$0$0
CONHSIP$0$826$0$0$0
CONCRPU$1300$0$0$0$0
Program Year Totals:$1,363$882$0$0 
Total FY23-FY26 Cost:$2,245Total FY23-FY34 Cost:$2,245 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
UTLPhase Approved by PMC
FDPhase Approved by PMC
CONPhase Approved by PMC
UTLStart of Phase2022-02-01
CONPhase on Approved STIP
FDPhase on Approved STIP
UTLPhase on Approved STIP
UTLCompletion of Phase2022-10-31
FDStart of Phase2023-03-31
UTLPlan to Utility Unit2023-05-01
FDPS+E to District Contract Management2023-12-01
FDCompletion of Phase2024-01-01
CONLet2024-03-14
CONAward Contract2024-04-13
CONStart of Phase2024-05-13
CONNotice to Proceed2024-05-13
CONPhysical Work Complete2025-07-01
CONCompletion of Phase2025-08-30
CONProject Agreement End Date2026-12-30