115428 | Sumneytown Pike Intersections Safety Improvements (Salford Township, Montgomery County)
The proposed scope of this project include:
¿ Install Exclusive Left-Turn Lanes at:
o Barndt Road (2 LTLs)
o Ridge Road/Skippack Road (2 LTLs)
¿ Remove Skew Angle of Ridge Road at Sumneytown Pike
¿ Install intersection lighting at Barndt Road and Ridge Road
Limits: Intersections of Sumneytown Pk and Barndt Rd, Ridge Rd/Skippack Rd
Air Quality Code: R1
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
PE | CRPU | $600 | $0 | $0 | $0 | $0 |
FD | HSIP | $197 | $0 | $0 | $0 | $0 |
ROW | HSIP | $0 | $144 | $0 | $0 | $0 |
UTL | HSIP | $0 | $0 | $719 | $0 | $0 |
CON | HSIP | $0 | $0 | $2186 | $0 | $0 |
Program Year Totals: | $797 | $144 | $2,905 | $0 | ||
Total FY23-FY26 Cost: | $3,846 | Total FY23-FY34 Cost: | $3,846 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
FD | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
UTL | Start of Phase | 2021-10-01 |
FD | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
ROW | Phase on Approved STIP | |
UTL | Phase on Approved STIP | |
ROW | Start of Phase | 2022-10-01 |
UTL | Completion of Phase | 2022-10-31 |
ROW | Completion of Phase | 2023-10-31 |
FD | Start of Phase | 2023-12-01 |
UTL | Plan to Utility Unit | 2024-04-01 |
ROW | Plan to ROW Unit | 2024-05-01 |
FD | Completion of Phase | 2025-08-25 |
FD | PS+E to District Contract Management | 2026-09-01 |
CON | Let | 2027-01-15 |
CON | Award Contract | 2027-02-14 |
CON | Start of Phase | 2027-03-16 |
CON | Notice to Proceed | 2027-03-16 |
CON | Physical Work Complete | 2028-09-01 |
CON | Completion of Phase | 2028-10-31 |
CON | Project Agreement End Date | 2030-03-02 |