115420 | Penndel Borough Intersection Improvements (Penndel Borough, Bucks County)
The proposed scope of this project include:
• Road diet of Lincoln Highway (SR 2037) from Lincoln Avenue to Durham Road (SR 0413)
• Addition of exclusive left-turn lane(s) at the following intersections:
o Lincoln Highway/Lincoln Avenue (westbound LTL)
o Lincoln Highway/Bellevue Avenue (eastbound/westbound LTLs and northbound/southbound LTLs)
o Lincoln Highway/Durham Road (westbound LTL)
• Prohibit eastbound Lincoln Highway (SR 2037) left-turn movements at Durham Road (SR 0413)
• Increase southbound Durham Road (SR 0413) left-turn lane storage at Lincoln Highway (SR 2037)
• Intersection control modification at Bellevue Avenue (SR 0413) and Durham Road (SR 0413)
• Modification of left-turn signal phasing at Lincoln Highway/Bellevue Avenue and Lincoln Highway/Durham Road signalized intersections
• Upgrade pavement markings and delineation within project limits
• Install high-visibility crosswalk markings at intersections within project limits
• Modernize signals along corridor, including interconnect with fiber optic and connection for accessibility from PennDOT Regional Traffic Management Center
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
CON | HSIP | $0 | $0 | $0 | $800 | $0 |
Program Year Totals: | $0 | $0 | $0 | $800 | ||
Total FY23-FY26 Cost: | $800 | Total FY23-FY34 Cost: | $800 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
FD | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
UTL | Start of Phase | 2021-10-01 |
UTL | Completion of Phase | 2022-02-01 |
FD | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
UTL | Phase on Approved STIP | |
FD | Start of Phase | 2022-12-15 |
UTL | Plan to Utility Unit | 2023-03-15 |
FD | PS+E to District Contract Management | 2025-01-15 |
CON | Let | 2025-05-22 |
CON | Award Contract | 2025-06-21 |
FD | Completion of Phase | 2025-07-21 |
CON | Start of Phase | 2025-07-21 |
CON | Notice to Proceed | 2025-07-21 |
CON | Physical Work Complete | 2026-09-01 |
CON | Completion of Phase | 2026-10-31 |
CON | Project Agreement End Date | 2028-03-01 |