❮ Back

114944 | Bethlehem Pike Safety Improvements (Springfield Township & Whitemarsh Township, Montgomery County)

Proposed improvements on Bethlehem Pike from Sunnybrook Road to Paper Mill Road include:
1) Converting partial limits of Bethlehem Pike from an undivided four-lane section to a three-lane section including a two-way-left-turn lane
2) Modify left-turn signal phasing (Change left-turn phase from at least one permissive approach to flashing yellow arrow (FYA))
3) Coordinate arterial signal
4) Add pedestrian countdown timers
5) Add retroreflective backplates to improve signal visibility

Limits: Sunnybrook Road to paper Mill Road
Air Quality Code: 2035M

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
PEHSIP$75$0$0$0$0
CONHSIP$1279$0$0$0$0
CONsHSIP$1497$0$0$0$0
Program Year Totals:$2,851$0$0$0 
Total FY23-FY26 Cost:$2,851Total FY23-FY34 Cost:$2,851 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
PEPhase Approved by PMC
CONPhase Approved by PMC
PE4232 Approved by FHWA
PEStart of Phase
PEN. E. P. A. Approval2022-07-01
PELevel 1A Categorical Exclusion
CONFinal Utility Clearance
PECompletion of Phase2022-08-26
CONPhase on Approved STIP
PEPhase on Approved STIP
CONLet2023-06-22
CONAward Contract2023-07-22
CONNotice to Proceed2023-07-31
CONStart of Phase2023-08-21
CONPhysical Work Complete2025-01-25
CONCompletion of Phase2025-03-26
CONProject Agreement End Date2026-07-26