113312 | US 1 Expressway Reconstruction: PA 41 to Schoolhouse Road (East Marlborough Township, Kennett Township, London Grove Township & New Garden Township, Chester County)

The project consists of pavement rehabilitation and reconstruction; guiderail upgrades; vertical and lateral clearance compliance corrections of overhead structures; and interchange improvements such as length of acceleration and deceleration lanes and loop ramp radii. Interchanges included in the work are at Newark Road, PA 82, and Baltimore Pike. See also MPMS #14580, #14581, and #113307.

Limits: PA 41 to Schoolhouse Road
Air Quality Code: S10

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
PE581$0$0$499$0$0
FD581$0$0$0$3245$4245
ROWNHPP$0$0$0$0$2706
ROWSTP$0$0$0$0$4919
UTLSTU$0$0$0$0$307
CONSTP$0$0$0$0$5380
CON581$0$0$0$0$6538
CONSTU$0$0$0$0$55451
CONNHPP$0$0$0$0$34920
Program Year Totals:$0$0$499$3,245 
Total FY23-FY26 Cost:$3,744Total FY23-FY34 Cost:$118,210 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
FDPhase Approved by PMC
CONPhase Approved by PMC
UTLPhase Approved by PMC
ROWPhase Approved by PMC
FDPhase on Approved STIP
CONPhase on Approved STIP
FDStart of Phase2024-10-15
UTLPlan to Utility Unit2025-02-15
ROWPlan to ROW Unit2025-08-15
FDPS+E to District Contract Management2027-08-15
CONLet2027-11-04
CONAward Contract2027-12-04
CONStart of Phase2028-01-03
CONNotice to Proceed2028-01-03
FDCompletion of Phase2028-01-03
CONPhysical Work Complete2030-01-31
CONCompletion of Phase2030-04-01
CONProject Agreement End Date2031-08-01