113307 | US 1 Expressway Reconstruction: PA/MD Line to PA 472 (West Nottingham Township, East Nottingham Township & Lower Oxford Township, Chester County)

The project consists of pavement rehabilitation and reconstruction; guiderail upgrades; vertical and lateral clearance compliance corrections of overhead structures; and interchange improvements such as length of acceleration and deceleration lanes and loop ramp radii. Interchanges included in the work are at Sylmar Road, Ridge Road, and PA 272. See also MPMS #14580, #14581, and #113312.

Limits: PA/MD Line to PA 472
Air Quality Code: S10

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
FDNHPP$5304$0$0$0$0
ROWNHPP$0$0$1080$0$0
ROW581$0$0$270$0$0
UTLSTP$0$219$0$0$0
UTL581$0$55$0$0$0
CONSTP$0$0$0$0$65143
CON581$0$0$0$0$18082
CONSTU$0$0$0$0$7209
Program Year Totals:$5,304$274$1,350$0 
Total FY23-FY26 Cost:$6,928Total FY23-FY34 Cost:$97,362 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
CONPhase Approved by PMC
ROWPhase Approved by PMC
UTLPhase Approved by PMC
FDPhase Approved by PMC
FDPhase on Approved STIP
ROWPhase on Approved STIP
UTLPhase on Approved STIP
FDStart of Phase2024-10-15
UTLPlan to Utility Unit2025-02-15
ROWPlan to ROW Unit2025-05-15
FDPS+E to District Contract Management2027-05-15
CONLet2027-08-15
CONAward Contract2027-09-14
CONStart of Phase2027-10-14
CONNotice to Proceed2027-10-14
FDCompletion of Phase2027-10-14
CONPhysical Work Complete2030-06-30
CONCompletion of Phase2030-08-29
CONProject Agreement End Date2031-12-29