❮ Back

112527 | Citywide ADA Ramps 3 (Philadelphia City)

This "Transition List" project will include the design and construction of ADA ramps that were originally included in the scope of other federal aid projects – primarily Center City Signals NE Quad (MPMS# 70014), completed in 2017, and the cancelled Citywide Bumpouts project (MPMS# 64805) – as well as various streetscape projects and ramps located on select Federal Aid routes that were repaved with local funding. These ramps typically would be included as design build items in the original project contracts, however, in some instances, the urban context of the ADA ramp locations warrants further coordination or study. To allow the original construction projects to proceed in a timely fashion, these ramps were pulled from the original construction contracts and will now be addressed as part of this transition list package. This will allow the City to design and construct the ramps to meet current ADA requirements while properly providing for stairs, cellar doors, unique paving materials, adjacent historic properties and other considerations as necessary.

Limits: City of Philadelphia
Air Quality Code: S10

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
FDSTP$1344$0$0$0$0
FDLOC$336$0$0$0$0
CONLOC$0$850$924$574$0
CONSTP$0$3402$3699$2297$0
Program Year Totals:$1,680$4,252$4,623$2,871 
Total FY23-FY26 Cost:$13,426Total FY23-FY34 Cost:$13,426 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
PEPhase Approved by PMC
CONPhase Approved by PMC
FDPhase Approved by PMC
PE4232 Approved by FHWA
PEStart of Phase2020-04-15
PECompletion of Phase2023-06-14
PEPhase on Approved STIP
CONPhase on Approved STIP
FDPhase on Approved STIP
PEN. E. P. A. Approval2023-05-15
FDStart of Phase2023-06-14
CONLet2024-02-15
CONAward Contract2024-03-16
CONNotice to Proceed2024-04-15
FDCompletion of Phase2024-04-15
CONStart of Phase2024-04-15
FDPS+E to District Contract Management2024-08-14
CONPhysical Work Complete2026-08-15
CONProject Agreement End Date2028-02-13
CONCompletion of Phase2028-07-23