112463 | ADA Ramps in Center City Philadelphia (Philadelphia City)
This project will involve the repair or reconstruction of damaged and or deteriorated ADA curb ramps in various historic districts in Philadelphia along Market, Chestnut, and Walnut Streets between the Delaware and Schuylkill River.
Limits: Market, Chestnut and Walnut Streets in Philadelphia
Air Quality Code: S10
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
PE | TOLL | $0 | $0 | $0 | $0 | $0 |
PE | STP | $0 | $150 | $0 | $0 | $0 |
UTL | TOLL | $0 | $0 | $0 | $0 | $0 |
UTL | STU | $0 | $22 | $0 | $0 | $0 |
CON | CRP | $2208 | $0 | $0 | $0 | $0 |
CON | STU | $0 | $980 | $0 | $0 | $0 |
CON | CRPU | $292 | $0 | $0 | $0 | $0 |
CON | TOLL | $0 | $0 | $0 | $0 | $0 |
Program Year Totals: | $2,500 | $1,152 | $0 | $0 | ||
Total FY23-FY26 Cost: | $3,652 | Total FY23-FY34 Cost: | $3,652 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
FD | Phase Approved by PMC | |
FD | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
CON | Phase Approved by PMC | |
UTL | Phase on Approved STIP | |
UTL | Phase Approved by PMC | |
UTL | Plan to Utility Unit | 2023-04-15 |
FD | Start of Phase | 2023-10-01 |
FD | PS+E to District Contract Management | 2023-10-01 |
CON | Let | 2023-12-14 |
CON | Award Contract | 2024-01-13 |
CON | Notice to Proceed | 2024-02-12 |
CON | Start of Phase | 2024-02-12 |
FD | Completion of Phase | 2024-02-12 |
CON | Physical Work Complete | 2025-06-20 |
CON | Completion of Phase | 2025-08-19 |
CON | Project Agreement End Date | 2026-12-19 |