The South Broad Street sidepath will connect NRG Station (formerly named Pattison Avenue and AT&T Station) to the Navy Yard through a sidepath on the west side of South Broad Street. The sidepath will run from Hartranft Street to the Navy Yard entrance at League Island Boulevard. To accommodate the sidepath near the Terminal Avenue intersection, the southbound lane configuration will be converted from two (2) left turn lanes and two (2) through lanes to one (1) left turn lane, one (1) shared left/through lane, and one (1) through lane. The project also proposes to include appropriate lighting, pavement markings and signage, and an upgrade of ADA facilities.

Limits: West side of South Broad Street, from Hartranft Street to the Navy Yard
Air Quality Code: A2

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
CONTAP$1537$0$0$0$0
CONTOLL$0$0$0$0$0
CONTAU$0$323$0$0$0
Program Year Totals:$1,537$323$0$0 
Total FY23-FY26 Cost:$1,860Total FY23-FY34 Cost:$1,860 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
CONPhase Approved by PMC
CONPhase on Approved STIP
CONLet2023-06-08
CONAward Contract2023-07-08
CONNotice to Proceed2023-08-07
CONStart of Phase2023-08-07
CONPhysical Work Complete2024-08-29
CONCompletion of Phase2024-10-28
CONProject Agreement End Date2026-02-27