111506 | Blvd Pedestrian Safety & Direct Bus Improvements (Philadelphia City)
This project will construct six (6) sidewalk segments for needed pedestrian improvements and prepare sites for Direct Bus stations; construct northbound Direct Bus station at Broad Street/Roosevelt Boulevard; make sidewalk improvements on Broad Street to improve pedestrian safety to the Broad Street Line.
Limits: Roosevelt Boulevard
Air Quality Code: A2
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
CON | TAP | $1531 | $0 | $0 | $0 | $0 |
CON | TAU | $0 | $701 | $0 | $0 | $0 |
Program Year Totals: | $1,531 | $701 | $0 | $0 | ||
Total FY23-FY26 Cost: | $2,232 | Total FY23-FY34 Cost: | $2,232 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
CON | Final Utility Clearance | |
CON | Phase on Approved STIP | |
CON | Start of Phase | 2023-01-30 |
CON | Notice to Proceed | 2023-01-30 |
CON | Let | 2023-07-13 |
CON | Award Contract | 2023-08-12 |
CON | Physical Work Complete | 2024-09-26 |
CON | Completion of Phase | 2024-11-25 |
CON | Project Agreement End Date | 2026-03-27 |