111496 | Franklin Square Pedestrian Access Project (Philadelphia City)

This project will construct curb bump-outs, pedestrian refuge islands, and expanded sidewalks to improve and increase pedestrian movement across Race Street and into Franklin Square.

Limits: Race Street: 6th St. - 8th St.
Air Quality Code: A2

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
CONTAU$850$430$0$0$0
CONTAP$432$0$0$0$0
CONTOLL$0$0$0$0$0
Program Year Totals:$1,282$430$0$0 
Total FY23-FY26 Cost:$1,712Total FY23-FY34 Cost:$1,712 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
CONPhase Approved by PMC
CONPhase on Approved STIP
CONLet2023-06-08
CONAward Contract2023-07-08
CONNotice to Proceed2023-08-07
CONStart of Phase2023-09-04
CONPhysical Work Complete2023-09-28
CONCompletion of Phase2023-11-27
CONProject Agreement End Date2025-03-28