111494 | Kriebel Road Trail (Towamencin Township, Montgomery County)
This project involves the construction of approximately 4,000 linear ft. of a new 10' wide pedestrian/bicycle trail from Trumbauer Rd to Valley View Way along the Towamencin Creek.
This project was funded via the 2018 Transportation Alternatives Set-aside Program.
Limits: Trumbauer Rd to Valley View Way
Air Quality Code: A2
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
CON | TAU | $131 | $0 | $0 | $0 | $0 |
Program Year Totals: | $131 | $0 | $0 | $0 | ||
Total FY23-FY26 Cost: | $131 | Total FY23-FY34 Cost: | $131 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
CON | Final Utility Clearance | |
CON | 4232 Approved by FHWA | |
CON | Let | 2021-08-12 |
CON | Award Contract | 2021-09-11 |
CON | Start of Phase | 2021-10-11 |
CON | Notice to Proceed | 2021-11-08 |
CON | Completion of Phase | 2023-03-07 |
CON | Phase on Approved STIP | |
CON | Physical Work Complete | 2023-05-18 |
CON | Project Agreement End Date | 2024-07-06 |