111488 | Media Borough Ridge Road Stormwater Improvements (Media Borough, Delaware County)
This project will install three Best Management practices (BMP) Green Infrastructure projects and enhance existing conveyance pipes to reduce flooding in north Media, making streets and sidewalks safer and improving the local water quality.
The project will take place in the north tip of Media Borough, from the intersection of N. Providence Road (SR 252) and Ridge Road, west on Ridge Road to N. Olive Street, and south on Olive to Eighth Street.
Air Quality Code: X9
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
CON | TAP | $0 | $400 | $0 | $0 | $0 |
Program Year Totals: | $0 | $400 | $0 | $0 | ||
Total FY23-FY26 Cost: | $400 | Total FY23-FY34 Cost: | $400 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
CON | Phase on Approved STIP | |
CON | Start of Phase | 2023-09-11 |
CON | Notice to Proceed | 2023-09-11 |
CON | Let | 2023-10-05 |
CON | Award Contract | 2023-11-04 |
CON | Physical Work Complete | 2024-08-30 |
CON | Completion of Phase | 2025-01-30 |
CON | Project Agreement End Date | 2026-02-28 |