111486 | Octoraro Trail Construction - Phase 1 (Concord Township, Delaware County)
Funding for this project will pay for the construction of Phase 1A of the multi-use Octoraro Trail in Concord Township from State Route 202 to Temple Road in Concord Township
Limits: State Route 202 to Temple Road
Air Quality Code: A2
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
CON | TAP | $0 | $0 | $1163 | $0 | $0 |
Program Year Totals: | $0 | $0 | $1,163 | $0 | ||
Total FY23-FY26 Cost: | $1,163 | Total FY23-FY34 Cost: | $1,163 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
CON | Phase on Approved STIP | |
CON | Award Contract | 2023-07-22 |
CON | Notice to Proceed | 2023-08-21 |
CON | Start of Phase | 2023-08-21 |
CON | Completion of Phase | 2025-05-15 |
CON | Project Agreement End Date | 2026-05-17 |