111486 | Octoraro Trail Construction - Phase 1 (Concord Township, Delaware County)

Funding for this project will pay for the construction of Phase 1A of the multi-use Octoraro Trail in Concord Township from State Route 202 to Temple Road in Concord Township

Limits: State Route 202 to Temple Road
Air Quality Code: A2

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
CONTAP$0$0$1163$0$0
Program Year Totals:$0$0$1,163$0 
Total FY23-FY26 Cost:$1,163Total FY23-FY34 Cost:$1,163 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
CONPhase Approved by PMC
CONPhase on Approved STIP
CONAward Contract2023-07-22
CONNotice to Proceed2023-08-21
CONStart of Phase2023-08-21
CONCompletion of Phase2025-05-15