111194 | Castor Avenue Corridor Safety Improvements (Philadelphia City)
This project will implement a road diet, upgrade signals, and add left turn lanes to the project area.
Limits: Castor Ave from Comly to Rhawn Ave
Air Quality Code: S6
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
FD | HSIP | $206 | $244 | $0 | $0 | $0 |
FD | TOLL | $0 | $0 | $0 | $0 | $0 |
CON | TOLL | $0 | $0 | $0 | $0 | $0 |
CON | HSIP | $0 | $1971 | $0 | $0 | $0 |
Program Year Totals: | $206 | $2,215 | $0 | $0 | ||
Total FY23-FY26 Cost: | $2,421 | Total FY23-FY34 Cost: | $2,421 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
FD | Start of Phase | 2020-05-28 |
CON | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
FD | 4232 Approved by FHWA | |
CON | Phase on Approved STIP | |
FD | Phase on Approved STIP | |
FD | PS+E to District Contract Management | 2024-07-15 |
CON | Let | 2024-10-10 |
CON | Award Contract | 2024-11-09 |
CON | Notice to Proceed | 2024-12-09 |
CON | Start of Phase | 2024-12-09 |
FD | Completion of Phase | 2024-12-09 |
CON | Physical Work Complete | 2026-08-31 |
CON | Completion of Phase | 2026-10-30 |
CON | Project Agreement End Date | 2028-02-29 |