111024 | Easton Road Roundabouts (Doylestown Borough, Bucks County)
Roundabout installation at Easton Rd (SR 1001) and New Britain Rd as well as Easton Rd and Sauerman Road.
Limits: Easton Rd and New Britain Rd; Easton Rd and Sauerman Rd
Air Quality Code: 2025M
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
CON | sHSIP | $1375 | $1000 | $0 | $0 | $0 |
CON | CAQ | $0 | $2125 | $0 | $0 | $0 |
Program Year Totals: | $1,375 | $3,125 | $0 | $0 | ||
Total FY23-FY26 Cost: | $4,500 | Total FY23-FY34 Cost: | $4,500 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
UTL | Start of Phase | 2019-06-27 |
UTL | Completion of Phase | 2019-12-31 |
UTL | Plan to Utility Unit | 2021-07-01 |
CON | Phase on Approved STIP | |
UTL | Phase on Approved STIP | |
UTL | 4232 Approved by FHWA | |
UTL | Conditional Utility Clearance | |
CON | Final ROW Clearance | |
CON | Final Utility Clearance | |
CON | Notice to Proceed | 2023-06-12 |
CON | Let | 2023-06-15 |
CON | Award Contract | 2023-07-15 |
CON | Start of Phase | 2023-08-15 |
CON | Physical Work Complete | 2024-07-12 |
CON | Completion of Phase | 2024-09-10 |
CON | Project Agreement End Date | 2026-01-10 |