❮ Back

110958 | Castor Avenue Roundabout (Philadelphia City)

Roundabout installation at Castor Avneue (SR 1005) and Wyoming Avenue

Limits: Castor Avneue (SR 1005) and Wyoming Avenue
Air Quality Code: 2035M

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
ROWsHSIP$0$50$0$0$0
CONsHSIP$0$262$500$0$0
Program Year Totals:$0$312$500$0 
Total FY23-FY26 Cost:$812Total FY23-FY34 Cost:$812 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
CONPhase Approved by PMC
CONFinal Utility Clearance
CONPhase on Approved STIP
CONLet2024-09-12
CONAward Contract2024-10-12
CONStart of Phase2024-11-11
CONNotice to Proceed2024-11-11
CONPhysical Work Complete2025-12-15
CONCompletion of Phase2026-02-13
CONProject Agreement End Date2027-06-15