110958 | Castor Avenue Roundabout (Philadelphia City)
Roundabout installation at Castor Avneue (SR 1005) and Wyoming Avenue
Limits: Castor Avneue (SR 1005) and Wyoming Avenue
Air Quality Code: 2035M
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
ROW | sHSIP | $0 | $50 | $0 | $0 | $0 |
CON | sHSIP | $0 | $262 | $500 | $0 | $0 |
Program Year Totals: | $0 | $312 | $500 | $0 | ||
Total FY23-FY26 Cost: | $812 | Total FY23-FY34 Cost: | $812 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
CON | Final Utility Clearance | |
CON | Phase on Approved STIP | |
CON | Let | 2024-09-12 |
CON | Award Contract | 2024-10-12 |
CON | Start of Phase | 2024-11-11 |
CON | Notice to Proceed | 2024-11-11 |
CON | Physical Work Complete | 2025-12-15 |
CON | Completion of Phase | 2026-02-13 |
CON | Project Agreement End Date | 2027-06-15 |