110775 | Kennett Safer Active Trans(L) (Chester County)
This project will install bicycle and pedestrian facilities.
2018 TA set aside regionally selected project, award amount $915,000
Limits: Walnut, Broad and South Streets
Air Quality Code: A2
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
CON | TAU | $992 | $0 | $0 | $0 | $0 |
Program Year Totals: | $992 | $0 | $0 | $0 | ||
Total FY23-FY26 Cost: | $992 | Total FY23-FY34 Cost: | $992 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
CON | Final Utility Clearance | |
CON | 4232 Approved by FHWA | |
CON | Phase on Approved STIP | |
CON | Completion of Phase | 2024-05-14 |
CON | Let | 2023-04-13 |
CON | Award Contract | 2023-05-13 |
CON | Notice to Proceed | 2023-07-10 |
CON | Start of Phase | 2023-07-10 |
CON | Physical Work Complete | 2024-03-15 |
CON | Project Agreement End Date | 2025-09-13 |