110775 | Kennett Safer Active Trans(L) (Chester County)

This project will install bicycle and pedestrian facilities.
2018 TA set aside regionally selected project, award amount $915,000

Limits: Walnut, Broad and South Streets
Air Quality Code: A2

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
CONTAU$992$0$0$0$0
Program Year Totals:$992$0$0$0 
Total FY23-FY26 Cost:$992Total FY23-FY34 Cost:$992 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
CONPhase Approved by PMC
CONFinal Utility Clearance
CON4232 Approved by FHWA
CONPhase on Approved STIP
CONCompletion of Phase2024-05-14
CONLet2023-04-13
CONAward Contract2023-05-13
CONNotice to Proceed2023-07-10
CONStart of Phase2023-07-10
CONPhysical Work Complete2024-03-15
CONProject Agreement End Date2025-09-13