110765 | Pickering Dam Road over Branch of Pickering Creek (Charlestown Township, Chester County)
This project involves rehabilitating or replacing the Bridge at Pickering Dam Road over Branch Pickering Creek.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state
Categorical Exclusion clearance.
Air Quality Code: S19
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
PE | 581 | $100 | $0 | $0 | $0 | $0 |
FD | 581 | $0 | $0 | $0 | $140 | $0 |
FD | 185 | $0 | $0 | $10 | $0 | $0 |
ROW | 581 | $0 | $0 | $0 | $0 | $75 |
UTL | 581 | $0 | $0 | $0 | $0 | $30 |
CON | 185 | $0 | $0 | $0 | $0 | $360 |
CON | 581 | $0 | $0 | $0 | $0 | $1442 |
Program Year Totals: | $100 | $0 | $10 | $140 | ||
Total FY23-FY26 Cost: | $250 | Total FY23-FY34 Cost: | $2,157 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
UTL | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
PE | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
FD | Phase on Approved STIP | |
PE | Phase on Approved STIP | |
PE | Start of Phase | 2022-10-01 |
FD | Start of Phase | 2024-04-10 |
PE | N. E. P. A. Approval | 2024-04-10 |
UTL | Plan to Utility Unit | 2024-04-10 |
ROW | Plan to ROW Unit | 2024-04-10 |
PE | Completion of Phase | 2024-10-01 |
UTL | Start of Phase | 2024-10-02 |
ROW | Start of Phase | 2024-10-02 |
FD | PS+E to District Contract Management | 2025-04-10 |
CON | Let | 2025-10-09 |
ROW | Completion of Phase | 2025-10-30 |
FD | Completion of Phase | 2025-10-30 |
UTL | Completion of Phase | 2025-10-30 |
CON | Award Contract | 2025-11-08 |
CON | Notice to Proceed | 2025-12-08 |
CON | Start of Phase | 2025-12-08 |
CON | Physical Work Complete | 2026-10-10 |
CON | Project Agreement End Date | 2027-04-10 |
CON | Completion of Phase | 2027-12-31 |