110763 | Cold Spring Crmry Rd over Branch Pine Run (Buckingham Township, Bucks County)
This project involves rehabilitating or replacing the Bridge atCold Spring Creamery Road over Branch Pine Run.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state
Categorical Exclusion clearance.
Air Quality Code: S19
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
PE | 185 | $0 | $116 | $0 | $0 | $0 |
FD | 185 | $0 | $0 | $179 | $0 | $0 |
ROW | 185 | $0 | $0 | $0 | $92 | $0 |
UTL | 185 | $0 | $0 | $0 | $0 | $25 |
CON | 185 | $0 | $0 | $0 | $0 | $1500 |
Program Year Totals: | $0 | $116 | $179 | $92 | ||
Total FY23-FY26 Cost: | $387 | Total FY23-FY34 Cost: | $1,912 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
PE | Start of Phase | 2023-09-30 |
UTL | Phase Approved by PMC | |
PE | Phase Approved by PMC | |
ROW | Phase on Approved STIP | |
FD | Phase Approved by PMC | |
FD | Phase on Approved STIP | |
PE | Phase on Approved STIP | |
CON | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
PE | Completion of Phase | 2025-09-30 |
UTL | Start of Phase | 2023-09-30 |
FD | Start of Phase | 2023-09-30 |
PE | N. E. P. A. Approval | 2023-09-30 |
UTL | Plan to Utility Unit | 2023-09-30 |
ROW | Plan to ROW Unit | 2024-09-30 |
ROW | Start of Phase | 2024-09-30 |
FD | PS+E to District Contract Management | 2025-03-30 |
CON | Let | 2025-09-25 |
CON | Award Contract | 2025-10-25 |
CON | Start of Phase | 2025-11-24 |
CON | Notice to Proceed | 2025-11-24 |
FD | Completion of Phase | 2025-11-24 |
CON | Physical Work Complete | 2026-09-25 |
CON | Completion of Phase | 2027-06-30 |
UTL | Completion of Phase | 2031-10-01 |
ROW | Completion of Phase | 2031-10-01 |