110444 | Ridge Pike - School Lane to Belvoir Road (CB #0 and TPK Bridge DB-116)/Interchange Area Bridges (Plymouth Township, Montgomery County)
This project is the combined replacement of Montgomery County Bridge #0 and PA Turnpike Bridge DB-116. County Bridge #0 carries Ridge Pike over Norfolk Southern and is 200 feet east of PA Turnpike Bridge DB-116, which carries Ridge Pike over the I-276/Pa Turnpike. Both structures flank the Eastbound On and Eastbound Off Ramps of the future Lafayette Street Interchange, and are in poor condition. This is a companion project to MPMS #48175 and #92839.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.
Limits: School Lane to Belvoir Road
Air Quality Code: S19
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
FD | STU | $360 | $0 | $0 | $0 | $0 |
FD | 183 | $508 | $0 | $0 | $0 | $0 |
FD | LOC | $132 | $0 | $0 | $0 | $0 |
ROW | 183 | $3772 | $0 | $0 | $0 | $0 |
ROW | LOC | $946 | $0 | $0 | $0 | $0 |
ROW | STU | $200 | $0 | $0 | $0 | $0 |
UTL | LOC | $0 | $326 | $0 | $0 | $0 |
UTL | 183 | $0 | $326 | $0 | $0 | $0 |
CON | 183 | $0 | $0 | $187 | $375 | $2327 |
CON | TPK | $0 | $0 | $21050 | $0 | $0 |
CON | STP | $0 | $0 | $0 | $0 | $7907 |
CON | STU | $0 | $0 | $1000 | $2000 | $4500 |
CON | LOC | $0 | $0 | $63 | $125 | $775 |
Program Year Totals: | $5,918 | $652 | $22,300 | $2,500 | ||
Total FY23-FY26 Cost: | $31,370 | Total FY23-FY34 Cost: | $46,879 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
FD | Phase Approved by PMC | |
UTL | Plan to Utility Unit | |
ROW | 4232 Approved by FHWA | |
FD | 4232 Approved by FHWA | |
FD | Start of Phase | 2021-12-01 |
CON | Phase on Approved STIP | |
UTL | Phase on Approved STIP | |
ROW | Phase on Approved STIP | |
FD | Phase on Approved STIP | |
ROW | Plan to ROW Unit | 2023-03-01 |
FD | PS+E to District Contract Management | 2024-03-07 |
CON | Notice to Proceed | 2024-05-13 |
FD | Completion of Phase | 2024-05-13 |
CON | Start of Phase | 2024-05-13 |
CON | Let | 2025-01-09 |
CON | Award Contract | 2025-02-08 |
CON | Physical Work Complete | 2025-03-31 |
CON | Completion of Phase | 2025-05-30 |
CON | Project Agreement End Date | 2026-09-29 |