110444 | Ridge Pike - School Lane to Belvoir Road (CB #0 and TPK Bridge DB-116)/Interchange Area Bridges (Plymouth Township, Montgomery County)

This project is the combined replacement of Montgomery County Bridge #0 and PA Turnpike Bridge DB-116. County Bridge #0 carries Ridge Pike over Norfolk Southern and is 200 feet east of PA Turnpike Bridge DB-116, which carries Ridge Pike over the I-276/Pa Turnpike. Both structures flank the Eastbound On and Eastbound Off Ramps of the future Lafayette Street Interchange, and are in poor condition. This is a companion project to MPMS #48175 and #92839.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.

Limits: School Lane to Belvoir Road
Air Quality Code: S19

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
FDSTU$360$0$0$0$0
FD183$508$0$0$0$0
FDLOC$132$0$0$0$0
ROW183$3772$0$0$0$0
ROWLOC$946$0$0$0$0
ROWSTU$200$0$0$0$0
UTLLOC$0$326$0$0$0
UTL183$0$326$0$0$0
CON183$0$0$187$375$2327
CONTPK$0$0$21050$0$0
CONSTP$0$0$0$0$7907
CONSTU$0$0$1000$2000$4500
CONLOC$0$0$63$125$775
Program Year Totals:$5,918$652$22,300$2,500 
Total FY23-FY26 Cost:$31,370Total FY23-FY34 Cost:$46,879 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
CONPhase Approved by PMC
UTLPhase Approved by PMC
ROWPhase Approved by PMC
FDPhase Approved by PMC
UTLPlan to Utility Unit
ROW4232 Approved by FHWA
FD4232 Approved by FHWA
FDStart of Phase2021-12-01
CONPhase on Approved STIP
UTLPhase on Approved STIP
ROWPhase on Approved STIP
FDPhase on Approved STIP
ROWPlan to ROW Unit2023-03-01
FDPS+E to District Contract Management2024-03-07
CONNotice to Proceed2024-05-13
FDCompletion of Phase2024-05-13
CONStart of Phase2024-05-13
CONLet2025-01-09
CONAward Contract2025-02-08
CONPhysical Work Complete2025-03-31
CONCompletion of Phase2025-05-30
CONProject Agreement End Date2026-09-29