110315 | Philmont Avenue/Tomlinson Road/Pine Road Improvements - 6 Point Intersection (Lower Moreland Township, Montgomery County)
This project proposes to streamline the six-legged intersection of Philmont/Tomlinson/Pine Roads in two stages by removing both legs of Tomlinson Road from the intersection and relocating them. Stage 1 would realign the northern leg of Tomlinson Road into Pine Road, and straighten out both Pine Road approaches to Philmont. Stage 2 will realign the southern leg of Tomlinson Road into a new intersection with Philmont Avenue 700 feet east of the original location. Additional shoulder and turning lane improvements along Philmont Avenue and Pine Road are also proposed.
Limits: Philmont Avenue/Tomlinson Road/Pine Road
Air Quality Code: R3
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
FD | 581 | $1591 | $0 | $0 | $0 | $0 |
ROW | 581 | $0 | $538 | $200 | $0 | $0 |
UTL | 581 | $0 | $250 | $100 | $450 | $400 |
CON | TOLL | $0 | $0 | $0 | $0 | $0 |
CON | STU | $0 | $0 | $0 | $0 | $17735 |
Program Year Totals: | $1,591 | $788 | $300 | $450 | ||
Total FY23-FY26 Cost: | $3,129 | Total FY23-FY34 Cost: | $21,264 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
FD | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
FD | Start of Phase | 2022-04-03 |
FD | Phase on Approved STIP | |
ROW | Phase on Approved STIP | |
UTL | Phase on Approved STIP | |
ROW | Plan to ROW Unit | 2023-05-01 |
UTL | Plan to Utility Unit | 2023-10-12 |
FD | PS+E to District Contract Management | 2025-01-03 |
CON | Let | 2025-04-10 |
CON | Award Contract | 2025-05-10 |
FD | Completion of Phase | 2025-06-09 |
CON | Start of Phase | 2025-06-09 |
CON | Notice to Proceed | 2025-06-09 |
CON | Physical Work Complete | 2026-12-01 |
CON | Completion of Phase | 2027-01-30 |
CON | Project Agreement End Date | 2028-05-31 |