110314 | 30th Street Viaduct over 30th Street Lower (Bridge) (Philadelphia City)

The purpose of the project is to rehabilitate the 30th Street Viaduct over 30th Street Lower between Market Street and Walnut Street to extend the useful life of the bridge. Work is planned to include deck replacement, superstructure and substructure cleaning & repair, and possible further rehabilitation. The underside of the bridge superstructure will be cleaned and repainted, with steel repairs as necessary. The bridge's drainage system will also be replaced and upgraded as needed. Recent bridge repairs have revealed accelerated deterioration of the structure, which will continue to worsen without rehabilitation, and could result in eventual weight restrictions or closure. Recent high-density development in the area has increased use of the viaduct, and pending future developments in the 30th Street Station area will further increase its importance, making future restrictions or closures highly disruptive.
A final alternative for bridge rehabilitation or replacement is determined upon federal National Environmental Policy Act (NEPA) or state Categorical Exclusion clearance.

Limits: Market Street and Walnut Street
Air Quality Code: S19

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
PE183$0$71$0$0$0
PELOC$0$23$0$0$0
PEBOF$0$377$0$0$0
FD183$179$0$0$0$0
FDLOC$60$0$0$0$0
FDBOF$1199$0$0$0$0
UTL183$0$11$0$0$0
UTLLOC$0$4$0$0$0
UTLBOF$0$60$0$0$0
CONBOF$0$0$6684$3000$3684
CONLOC$0$0$417$187$368
CON183$0$0$1253$562$690
Program Year Totals:$1,438$546$8,354$3,749 
Total FY23-FY26 Cost:$14,087Total FY23-FY34 Cost:$18,829 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
PEPhase Approved by PMC
CONPhase Approved by PMC
FDPhase Approved by PMC
PE4232 Approved by FHWA
UTLPhase Approved by PMC
PEStart of Phase2020-12-01
PECompletion of Phase2023-10-31
FDPhase on Approved STIP
PEPhase on Approved STIP
CONPhase on Approved STIP
UTLPhase on Approved STIP
PEN. E. P. A. Approval2023-10-01
FDStart of Phase2023-11-01
CONLet2025-07-16
CONAward Contract2025-08-15
CONStart of Phase2025-09-14
CONNotice to Proceed2025-09-14
FDCompletion of Phase2025-11-17
CONPhysical Work Complete2028-12-22
CONCompletion of Phase2029-02-20
CONProject Agreement End Date2030-06-22