108092 | Citywide Resurfacing 107 (Philadelphia City)

Roadway surface conditions along the project's street sections have deteriorated over time due to traffic, weather conditions, and utility excavations. As such, the primary purpose of the project is to restore roadway surfaces to fully functional and optimal conditions; to provide smoother riding surfaces for enhanced traffic movement; to install pavement markings for better direction for motorists, bicyclists, and pedestrians; and to upgrade non-compliant ADA ramps at crosswalks to current standards. The work will increase the service life of these roadways and reduce future maintenance costs.

All street segments will be milled and resurfaced with bituminous material and restriped. Any ground disturbance will occur within the existing right-of-way and will be limited to the cartway and sidewalks in the various corridors. In most cases, pavement restoration in the disturbed areas will match existing pavement types.
Streets included in this resurfacing package include:
Minerva Street (G184) from Umbria Street to Shawmont Avenue
Morris Street (G012) from Front Street to 34th Street
Race Street (G010) from Benjamin Franklin Parkway to Broad Street
Race Street (G010) from 6th Street to 2nd Street
Red Lion Road (G164) from Verree Road to Roosevelt Boulevard
Shawmont Avenue (G184) from Minerva Street to Ridge Avenue
Tasker Street (G014) from Front Street to 34th Street
Umbria Street (G184) from Leverington Avenue to Minerva Street
Washington Avenue (G016) from Grays Ferry Avenue to Delaware Avenue

Limits: City of Philadelphia
Air Quality Code: S10

FY2023 TIP for PA Program Years (in Thousands)

PhaseFundFY23FY24FY25FY26FY27-34
PESTU$250$0$0$0$0
CONSTU*$4541$0$0$0$0
Program Year Totals:$4,791$0$0$0 
Total FY23-FY26 Cost:$4,791Total FY23-FY34 Cost:$4,791 
All costs in thousands.

Milestones

PhaseMilestoneEstimated Date
CONPhase Approved by PMC
CONFinal Utility Clearance
CON4232 Approved by FHWA
CONLet2021-12-09
CONAward Contract2022-02-10
CONStart of Phase2022-03-10
CONNotice to Proceed2022-03-07
CONPhase on Approved STIP
CONCompletion of Phase2023-08-14
CONPhysical Work Complete2023-09-10
CONProject Agreement End Date2024-12-13