107945 | Art School Rd O/ Br Pickering Creek (Bridge) (West Pikeland Township, Chester County)
This project will include the removal and replacement of an existing poor condition, weight restricted bridge along Art School Road in West Pikeland Township, Chester County.
Limits: West Pikeland Township
Air Quality Code: S19
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
ROW | BOF | $169 | $0 | $0 | $0 | $0 |
ROW | TOLL | $0 | $0 | $0 | $0 | $0 |
UTL | TOLL | $0 | $0 | $0 | $0 | $0 |
UTL | BOF | $56 | $0 | $0 | $0 | $0 |
CON | TOLL | $0 | $0 | $0 | $0 | $0 |
CON | BOF | $2745 | $69 | $0 | $0 | $0 |
Program Year Totals: | $2,970 | $69 | $0 | $0 | ||
Total FY23-FY26 Cost: | $3,039 | Total FY23-FY34 Cost: | $3,039 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
CON | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
UTL | Start of Phase | 2018-02-14 |
ROW | Start of Phase | 2018-02-14 |
UTL | Completion of Phase | 2018-12-13 |
ROW | Completion of Phase | 2018-12-13 |
UTL | Phase on Approved STIP | |
ROW | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
ROW | Plan to ROW Unit | 2023-08-10 |
UTL | Plan to Utility Unit | 2023-08-10 |
CON | Let | 2024-10-10 |
CON | Award Contract | 2024-11-09 |
CON | Notice to Proceed | 2024-12-09 |
CON | Start of Phase | 2024-12-09 |
CON | Physical Work Complete | 2025-10-10 |
CON | Completion of Phase | 2025-12-09 |
CON | Project Agreement End Date | 2027-04-10 |