107794 | Langhorne Yardley Road at Woodbourne Road and Bridgetown Pike Intersection Improvements (Middletown Township, Bucks County)
The proposed roadway improvements for the intersection of Woodbourne Road (SR 2033) & Langhorne-Yardley Road (SR 2049) will include the addition of left turn lanes and right turn lanes, and improved alignment of the Woodbourne Road lanes at the intersection. The signal equipment will be replaced and modernized. For the T intersection of Langhorne-Yardley Road (SR 2049) & Bridgetown Pike (SR 2010), the improvements will include a roundabout.
This project had previously been listed under MPMS #57624.
Limits: Woodbourne Road/Langhorne-Yardley Rd to intersection of Langhorne-Yardley Rd/Bridgetown Pike
Air Quality Code: 2035M
Phase | Fund | FY23 | FY24 | FY25 | FY26 | FY27-34 |
---|---|---|---|---|---|---|
FD | LOC | $633 | $0 | $0 | $0 | $0 |
ROW | STU | $530 | $0 | $0 | $0 | $0 |
UTL | STU | $557 | $0 | $0 | $0 | $0 |
CON | 581 | $0 | $1205 | $1124 | $0 | $0 |
CON | STU | $0 | $4822 | $4496 | $0 | $0 |
Program Year Totals: | $1,720 | $6,027 | $5,620 | $0 | ||
Total FY23-FY26 Cost: | $13,367 | Total FY23-FY34 Cost: | $13,367 | |||
All costs in thousands. |
Phase | Milestone | Estimated Date |
---|---|---|
FD | Phase Approved by PMC | |
UTL | Phase Approved by PMC | |
CON | Phase Approved by PMC | |
ROW | Phase Approved by PMC | |
UTL | Start of Phase | 2018-11-30 |
UTL | Completion of Phase | 2019-11-29 |
ROW | Start of Phase | 2019-11-29 |
ROW | 4232 Approved by FHWA | |
ROW | Plan to ROW Unit | 2021-12-17 |
FD | Start of Phase | 2021-11-26 |
ROW | Phase on Approved STIP | |
CON | Phase on Approved STIP | |
UTL | Phase on Approved STIP | |
FD | Phase on Approved STIP | |
UTL | Plan to Utility Unit | 2021-11-19 |
UTL | 4232 Approved by FHWA | |
FD | PS+E to District Contract Management | 2023-05-12 |
CON | Let | 2023-08-10 |
CON | Award Contract | 2023-09-09 |
CON | Start of Phase | 2023-10-09 |
CON | Notice to Proceed | 2023-10-09 |
FD | Completion of Phase | 2023-10-23 |
CON | Physical Work Complete | 2025-10-31 |
CON | Completion of Phase | 2025-12-30 |
CON | Project Agreement End Date | 2027-05-01 |